Pouring with rain today but we had to finish preparing for tomorrows concrete pour

Firstly we prepared the threshold strip - (80 x 80 mm angle) that gives a small lip to the front edge of the slab to stop rain being driven under the roller shutter. This was welded onto the pillars either side of the main door and continues across to the pedestrian door.
Then the wooden shuttering to flank either side of the doors was made and pegged in place. Then the shuttering and threshold strip were backed up temporarily with crushed concrete to stop them moving.
Each pillar (12 of them) were made at our request with an extra hole at mid floor level, and we hooked a length of re-bar shaped like a walking stick through these to firmly anchor the slab and pillars together.
Then finally Darren cut slots in the rear shuttering for the exits from the roof gullies and placed a short length of 110 mm pipe into them ready to connect up after the concrete is laid.
A last tidy up to make room for the six concrete lorries and pump to turn - last time we had a concrete pump here he demolished the corner of one of my Portakabins

I've even evicted the cottage guests from their normal parking places to avoid disasters (hopefully) when they all start rolling in tomorrow morning at 07:30
Forecast is for fine weather in the morning - let's hope they've got it right !